New Moore Road Interchange Could Break Ground by 2029, RTA Executive Tells Marana

MARANA, Arizona. — Construction on a new Interstate 10 interchange at Moore Road could begin as early as 2029, with completion targeted for 2031, clearing the way for a rebuilt Tangerine Road interchange and later work at Cortaro Road.

Mike Ortega, executive director of the Regional Transportation Authority and the Pima Association of Governments, laid out that sequence on the Nov. 16 episode of Inside Marana, hosted by Marana Mayor Jon Post. The Marana projects are part of RTA Next, the 20-year, $2.67 billion regional transportation plan voters approved this year.

“To do an interchange in five years is almost unheard of,” Ortega said of the Moore Road timeline.

Moore Road first, then Tangerine and Cortaro

Ortega said Moore Road is being built first because it can go up on open land without shutting down an existing road, and it will serve as the detour when the Tangerine Road interchange is torn down and rebuilt. He said rebuilding Marana’s interchanges without that reliever would only push more traffic onto routes not built to handle it.

The project is now in planning and early design, and building it should take about a year to a year and a half, Ortega said. Post said Tangerine construction could follow in 2031 as Moore Road nears completion.

Cortaro Road, which Ortega called the most complex of the three because of the railroad, utilities and nearby businesses, is scheduled later in the plan. He said the RTA wants to move it up when opportunities arise and is already talking with the Arizona Department of Transportation to keep it “on the radar.” Post put past cost estimates at about $350 million; Ortega said he has seen figures above $250 million.

Other Marana projects in the plan

RTA Next will finish Tangerine Road up to Thornydale Road, a leftover from the first RTA plan that crosses Oro Valley, unincorporated Pima County and Marana, Ortega said. He said the railroad crossing has been the main schedule challenge, and that the RTA is arranging an in-person meeting with railroad officials and suggested letters of support from mayors across the region.

Post said Ina Road will be modernized by restriping within existing pavement rather than widened, with the savings moved to projects farther north. He said the town is also exploring a fund to help revitalize the Ina Road area and an alternate route between Cortaro and Ina for east-side residents during construction.

Ortega said Marana will also have access to new pots of money for pavement rehabilitation, safety and accessibility, and bike and pedestrian improvements. Pavement rehab was added after residents asked for existing roads to be fixed, not just new ones built, he said.

RTA to take a hands-on role in delivery

Under the first RTA plan, the authority mainly acted as “the bank” and left delivery to each jurisdiction, Ortega said. Under RTA Next, he said, the RTA will offer to help with planning, design and right-of-way purchases, and will give the board regular progress updates.

“The reality is that the RTA is responsible for all aspects of delivery of the program,” Ortega said. He said the City of Tucson has already asked the RTA to deliver work on North First Avenue and Houghton Road.

A citizens’ panel, the Citizens Accountability for Regional Transportation committee, will monitor whether the plan is carried out as voters approved, and any change to a project or its cost must go back to voters, Ortega said.

By the numbers:

  • $2.67 billion: size of the RTA Next plan, cut from more than $5 billion in requests, Ortega said
  • 38: road projects in the plan, 31 new and 7 carried over from the first RTA, over four five-year periods
  • $16 billion: the region’s estimated total transportation need, per a figure Ortega cited
  • About $1 billion: how far first-plan sales tax revenue fell short of projections, he said
  • About $50 million: regional federal and state funding PAG distributes a year, which returns to local jurisdictions starting in 2032

Lessons from the first plan

Ortega said the 2006 plan’s projects went unfinished because revenue never met projections in any year, with the Great Recession and the pandemic cutting into sales tax collections. The board covered about half the gap with regional funds and voters were asked to cover the rest, so all of the 2006 projects will be finished, he said.

This time, Ortega said, the board based the plan on the pessimistic forecast from the University of Arizona’s Eller College, and wrote down in advance where any extra revenue will go. “There’s no slush fund,” he said.

Inside Marana, hosted by Marana Mayor Jon Post, streams on the Live The Dream Media Streamverse Network and the free Live The Dream Media app.

Related posts

Third Carrier Group Tightens ‘Outside-In’ Squeeze on Iran, Retired Capt. Robert Wells Says

Youth Housing Nonprofit I Am You 360 to Open Second Small-Home Site With Anonymous Donor

Marana Plans Its Next Wave of Needed Parks and Wants Residents’ Input by Nov. 20